验证范围与正式验收 · PMP 练习题解析

范围管理 中等 Process 过程域 题号 PMP202611-650

题目

某软件实施项目已达成范围、进度与预算目标,UAT 完成、缺陷已修复或获接受。发起人在指导委员会上口头说“看起来完成了”,但尚无书面确认。下一步应当做什么?
A software implementation met scope, schedule and budget; UAT is complete and defects resolved or accepted. The sponsor verbally says 'this looks done' in a steering committee meeting, but there is no written confirmation. What should you do next?

选项

  1. A.Close the project in the PMIS and release the team, since the sponsor verbally approved
  2. B.Request the sponsor to send an email confirming completion and then archive the project documents
  3. C.Facilitate a formal acceptance and closure process based on the defined project approval requirements and exit criteria.
  4. D.Schedule a lessons learned meeting and then notify all stakeholders that the project is closed.
正确答案:C

解析

解析:正式验收必须依据既定的批准要求与退出准则留下文件记录,口头确认达不到治理要求。 Rationale:Formal acceptance must be documented against defined approval requirements and exit criteria; verbal confirmation is insufficient for governance standards.