题目
某软件产品已交付六个月。项目发起人请项目经理评估该产品是否在实现预期的业务价值。最合适的方法是?
A software product was delivered six months ago. The project sponsor asks the project manager to assess whether the product is delivering the intended business value. Which approach is most appropriate?
选项
- A.Compare the final project cost against the approved budget to determine financial success
- B.Review the product's key performance indicators against the success criteria defined in the benefits realization plan
- C.Conduct user satisfaction surveys as the sole measure of value delivery
- D.Count the number of features delivered versus originally planned to measure completeness
解析
解析:价值交付应依据效益实现计划中的成功标准衡量,而不只是预算符合度或功能数量等执行指标。追踪业务成果(收入增长、效率提升、满意度)的 KPI 才是合适的衡量方式。
Rationale:Value delivery is measured against the success criteria defined in the benefits realization plan, not just execution metrics like budget adherence or feature count. KPIs tracking business outcomes—revenue growth, efficiency gains, satisfaction—are the right measures.