题目
你的项目处于高度不确定的环境中。哪种方式能确保尽早交付商业价值?
Your project operates in a highly uncertain environment. Which approach ensures early delivery of business value?
选项
- A.Waterfall approach
- B.Predictive methodology
- C.Incremental or Agile delivery
- D.Multi-phase Waterfall
解析
解析:敏捷或增量方法使组织能在项目生命周期中更早交付较小颗粒的价值增量。
Rationale:Agile or incremental approaches allow organizations to deliver smaller increments of value earlier in the project lifecycle.