价值交付与最小可行 · PMP 练习题解析

敏捷与混合实践 中等 Process 过程域 题号 PMP202611-153

题目

项目启动会上,发起人说成功意味着“更快的客户入驻”,而团队认为成功是“按时上线新应用”。下一步最好做什么?
At the kick-off, the sponsor says success means "faster customer onboarding", while the team thinks success means "launching the new app on time". What is the best next step?

选项

  1. A.Follow the sponsor's view because the sponsor funds the project.
  2. B.Follow the team's view because they do the work.
  3. C.Run a workshop to agree on a common vision and measurable success criteria.
  4. D.Record both views and move on.
正确答案:C

解析

解析:建立共同愿景是考纲中人员领域的首要任务之一。带有可衡量成果的共同愿景能让所有人朝同一方向发力;忽视这一分歧只会在后续引发冲突。 Rationale:Developing a common vision is one of the first People tasks in the outline. A shared vision with measurable outcomes keeps everyone pulling in the same direction; ignoring the gap leads to conflict later.