题目
项目进行中,你发现组织可以在原范围之外获取额外价值。项目经理应该怎么做?
During the project, you identify a way the organisation could capture additional value beyond the original scope. What should the project manager do?
选项
- A.Raise the opportunity with the sponsor so it can be evaluated for the business.
- B.Add it to the project scope immediately.
- C.Keep it to yourself to avoid expanding the work.
- D.Implement it quietly and surprise the sponsor with the benefit.
解析
解析:把机会提交评估既尊重治理,也服务业务。擅自加入范围会绕过变更控制;闭口不言则让组织失去潜在价值。
Rationale:Raising the opportunity respects governance while serving the business. Adding it to scope unilaterally bypasses change control; staying silent denies the organisation potential value.