合同类型与条款 · PMP 练习题解析

采购管理 中等 Process 过程域 题号 PMP202611-642

题目

与供应商发生重大争议:项目经理称其未履行合同义务,供应商则抱怨付款滞后。最佳做法是:
A major dispute arises with a vendor: the PM claims the vendor failed to perform contractual obligations, while the vendor complains payments are behind. What is the best course of action?

选项

  1. A.Refer this issue to a third party for mediation or arbitration
  2. B.File a contract claim and then work directly with the vendor to resolve the issue
  3. C.Terminate the contract, document lessons learned, and find another vendor
  4. D.Conduct a procurement audit
正确答案:B

解析

解析:索赔管理帮助买卖双方达成一致、避免昂贵诉讼;直接协商是首选,调解/仲裁才是备选。 Rationale:Claims administration helps buyer and seller reach agreement and avoid costly litigation; direct negotiation is preferred, with ADR as fallback.