采购管理 困难 Process 过程域 题号 PMP202611-340

题目

某敏捷团队被要求为需求尚不清晰的新产品报出固定总价。最恰当的做法是什么?
An agile team is asked to provide a fixed-price quote for a new product with unclear requirements. What is the most appropriate approach?

选项

  1. A.Refuse the engagement since agile cannot work with contract constraints.
  2. B.Provide a fixed price based on the best available estimate, the team can manage scope later.
  3. C.Propose a time-and-materials or fixed-time/variable-scope contract instead, and explain that a fixed price for unclear requirements creates unacceptable risk for both parties.
  4. D.Pad the estimate significantly to cover all possible scope scenarios.
正确答案:C

解析

解析:C 正确。需求不清却签固定总价,风险全部转移给供方,还会诱导供方压缩范围而非交付客户价值。敏捷适配的做法是提出允许边做边学的合同结构:工时材料、分阶段固定价,或固定时间/可变范围。硬接风险(B)会给团队埋下冲突;直接拒绝(A)过于僵化;大幅加价(D)使报价失去竞争力,且属于不诚信。 Rationale:C is correct. Fixed-price contracts for unclear requirements shift all risk to the supplier and incentivise scope restriction rather than customer value delivery. The agile-appropriate approach is to propose contract structures that allow for learning: time-and-materials, phased fixed-price, or fixed-time/variable-scope. Accepting the risk (B) sets up the team for conflict. Refusing (A) is unnecessarily rigid. Excessive padding (D) makes the quote uncompetitive and is a form of dishonesty.