合同类型与条款 · PMP 练习题解析

采购管理 困难 Process 过程域 题号 PMP202611-296

题目

某固定总价项目合同规定:任何范围变更必须在实施前获得书面批准。客户口头提出变更并要求团队立即开工,承诺稍后补办手续。项目经理应该怎么做?
A contract for a fixed-price project states that any scope changes must be approved in writing before implementation. The client verbally requests a change and asks the team to start immediately, promising to formalise it later. What should the project manager do?

选项

  1. A.Do not start the change until the written change order is signed, as per the contract terms.
  2. B.Start the change but document the verbal approval as protection.
  3. C.Begin the change since the client has given verbal approval and formalisation is coming.
  4. D.Raise the change request internally and have the sponsor decide.
正确答案:A

解析

解析:A 正确。合同条款具有约束力。固定总价合同要求书面批准,就意味着没有书面授权不得开工——口头批准不具合同效力。在变更未获批准前开工,一旦变更单始终未补办或口头范围日后产生争议,组织将承担财务风险。PMI 的道德与职业标准也要求遵守合同义务。 Rationale:A is correct. Contract terms are binding. A fixed-price contract with written approval requirements means no work begins without written authorisation: verbal approval has no contractual standing. Starting work on an unapproved change exposes the organisation to financial risk if the change order is never formalised or if the scope of the verbal request is disputed later. PMI's ethics and professional standards reinforce following contractual obligations.