题目
某项目采用成本加固定费用(CPFF)合同。承包商的实际成本低于预期。谁受益?
A project is using a Cost-Plus-Fixed-Fee (CPFF) contract. The contractor's actual costs come in lower than expected. Who benefits?
选项
- A.The seller: the fixed fee is a larger percentage of actual costs.
- B.Neither: costs are fixed in a CPFF contract regardless of actual spend.
- C.The buyer: they pay lower actual costs plus the same fixed fee.
- D.Both equally: savings are split under a CPFF contract.
解析
解析:C 正确。CPFF 下,买方支付全部实际成本加固定费用。实际成本降低时,固定费用不变,但总支付额减少,因此买方受益,卖方仍得到固定利润。若为固定总价合同,成本节约归卖方(差价自留);而在 CPFF 下,成本节约归买方,卖方只拿可预期的固定利润。
Rationale:C is correct. Under a CPFF contract, the buyer pays all actual costs plus a fixed fee. If actual costs are lower, the buyer pays less total, the fixed fee stays the same but the overall payment is reduced. The seller still receives their fixed profit. Under a Fixed-Price contract, lower costs benefit the seller (they keep the difference). Under CPFF, the buyer holds the cost savings while the seller gets predictable profit.