合同类型与条款 · PMP 练习题解析

采购管理 中等 Process 过程域 题号 PMP202611-121

题目

某组织将定制移动应用的开发外包。项目范围界定清晰、技术成熟,且已有详细的需求文档。最合适的合同类型是?
An organization is outsourcing the development of a custom mobile application. The project scope is well-defined, the technology is mature, and detailed requirements documentation exists. Which contract type is most appropriate?

选项

  1. A.Time and Materials (T&M), because it provides flexibility for scope changes
  2. B.Cost Plus Fixed Fee (CPFF), because it protects the buyer from cost overruns
  3. C.Firm Fixed Price (FFP), because the scope is well-defined and cost-overrun risk transfers to the seller
  4. D.Cost Plus Incentive Fee (CPIF), because it motivates the seller to control costs
正确答案:C

解析

解析:固定总价合同最适用于范围与需求清晰的情形:买方按约定价格支付,与实际成本无关,从而把成本风险转移给卖方。工料合同适用于范围不确定;成本补偿类合同适用于不确定或高风险工作。 Rationale:Firm Fixed Price is most appropriate when scope and requirements are well defined; the buyer pays a set price regardless of actual seller costs, transferring cost risk to the seller. T&M suits undefined scope, and cost-reimbursable contracts suit uncertain or high-risk work.