题目
供应商交付的组件在技术上符合合同,但无法满足实际用户需求,而该需求当初描述得不充分。项目经理首先应该做什么?
A vendor delivers a component that technically meets the contract but does not satisfy the actual user need, which was poorly specified. What should the project manager do FIRST?
选项
- A.Acknowledge the contract was met and address the gap through a change to requirements.
- B.Reject the component and demand the vendor fix it for free.
- C.Accept the component and ignore the unmet user need.
- D.Withhold payment until the vendor satisfies the real need.
解析
解析:既然合同已履约,缺口就是需求问题,应通过变更控制解决,而非供应商的责任。要求免费做范围外的工作既不公平也难以执行;对合规交付扣款则容易引发争议。
Rationale:Since the contract was met, the gap is a requirements problem to fix through change control, not the vendor's fault. Demanding a free fix for out-of-scope work is unfair and likely unenforceable; withholding payment for compliant delivery invites a dispute.