合同类型与条款 · PMP 练习题解析

采购管理 中等 Process 过程域 题号 PMP202611-235

题目

供应商交付的组件在技术上符合合同,但无法满足实际用户需求,而该需求当初描述得不充分。项目经理首先应该做什么?
A vendor delivers a component that technically meets the contract but does not satisfy the actual user need, which was poorly specified. What should the project manager do FIRST?

选项

  1. A.Acknowledge the contract was met and address the gap through a change to requirements.
  2. B.Reject the component and demand the vendor fix it for free.
  3. C.Accept the component and ignore the unmet user need.
  4. D.Withhold payment until the vendor satisfies the real need.
正确答案:A

解析

解析:既然合同已履约,缺口就是需求问题,应通过变更控制解决,而非供应商的责任。要求免费做范围外的工作既不公平也难以执行;对合规交付扣款则容易引发争议。 Rationale:Since the contract was met, the gap is a requirements problem to fix through change control, not the vendor's fault. Demanding a free fix for out-of-scope work is unfair and likely unenforceable; withholding payment for compliant delivery invites a dispute.

同考点练习题