题目
某改造项目预算 10 万美元,已完成 40% 的工作,累计花费 6 万美元。若成本绩效保持不变,还需多少才能完工?
A renovation project budgeted at $100,000 has completed 40% of the work and spent $60,000. How much more will it cost to complete the project if cost performance remains unchanged?
选项
- A.$160,000
- B.$149,254
- C.$120,000
- D.$89,254
解析
解析:EV = 40% × 10 万 = 4 万;CPI = 4÷6 ≈ 0.667;EAC = BAC÷CPI ≈ 15 万;ETC = EAC − AC ≈ 8.93 万。注意问的是“还需多少”(ETC),不是完工总估(EAC)。
Rationale:EV = 40% × $100,000 = $40,000; CPI = EV/AC = 40/60 ≈ 0.667; EAC = BAC/CPI ≈ $150,000; ETC = EAC − AC ≈ $89,254.