题目
你想表彰部分高绩效成员的贡献。需要依据下列哪项来推进这项工作?
You want to recognize the contributions of some high-performing team members. Which of the following do you need to guide you through this process?
选项
- A.Organizational process assets
- B.Stakeholder register
- C.Project team assignments
- D.Quality metrics
解析
解析:管理团队会用到组织过程资产,例如表彰证书、企业纪念品与其他奖励安排,用以指导认可与激励。
Rationale:Manage Team uses organizational process assets such as certificates of appreciation, corporate apparel and perquisites to guide recognition.