合同类型与条款 · PMP 练习题解析

采购管理 中等 Process 过程域 题号 PMP202611-179

题目

你需要两名额外分析师工作三个月,而他们工作的具体范围尚不明确。哪种合同类型最合适?
You need two extra analysts for three months, and the exact scope of their work is not yet clear. Which contract type fits best?

选项

  1. A.Firm fixed price.
  2. B.Time and materials.
  3. C.Fixed price with incentive fee.
  4. D.Cost plus award fee for a large build.
正确答案:B

解析

解析:工料合同适用于范围尚未完全明确的短期人力增补。固定价格类合同要求范围清晰,成本加费类更适合规模更大、更复杂的建设。 Rationale:Time and materials suits short-term staff augmentation where scope is not fully defined. Fixed-price types need a well-defined scope, and cost-plus arrangements fit larger, more complex builds.