对于范围不清晰的项目,哪种合同类型给买方带来的风险最大?
For a project with an unclear scope, which contract type carries the most risk for the buyer?
选项
- A.Fixed Price
- B.Cost Plus Fixed Fee (CPFF)
- C.Time and Materials (T&M)
- D.Firm Fixed Price (FFP)
解析
解析:在成本补偿类合同中,项目成本由买方承担,因此成本超支的风险落在买方身上。
Rationale:In cost-reimbursable contracts, the buyer covers project costs, meaning they carry the risk of cost overruns.