题目
你需要供应商开发一个早期原型。范围不清晰,且很可能在用户测试后发生变化,但你仍希望控制预算。哪种合同类型最合适?
You need a vendor to build an early prototype. The scope is unclear and will likely change after user testing. You still want to protect the budget. Which contract type fits best?
选项
- A.Firm fixed price
- B.Time and materials with a not-to-exceed limit
- C.Fixed price with economic price adjustment
- D.Cost-plus award fee for a multi-year program
解析
解析:工料合同适合范围不清晰的工作,设置“不得超支”上限可锁定成本。固定总价合同需要清晰范围,否则卖方会加入高额风险溢价;价格调整型合同适用于市场价格会变动的长期合同。
Rationale:Time and materials suits work with unclear scope, and a not-to-exceed limit caps cost. A firm-fixed-price contract needs a clear scope, or the seller will add large risk margins. Price adjustment contracts are for long contracts where market prices change.