题目
项目将从组织外部采购货物与服务。项目经理要求团队列出与这些采购相关的完整风险清单。最佳做法是:
The project will procure goods and services from outside the organization. The PM has asked the team to develop a comprehensive list of individual risks related to those procurements. What is the best course of action?
选项
- A.Consult the project charter
- B.Review procurement documentation
- C.Develop a procurement register
- D.Check the probability and impact matrix
解析
解析:外部采购会引入成本、进度、质量、依赖、合规与履约等风险,识别这些风险应回到采购文件。
Rationale:External procurement introduces cost, schedule, quality, dependency, compliance and performance risks; procurement documentation is the source for identifying them.