供方选择与采购流程 · PMP 练习题解析

采购管理 中等 Process 过程域 题号 PMP202611-559

题目

要弄清项目关闭合同需要执行哪些活动,应当查阅哪里?
Where would you look to find what activities should be performed to close out contracts on your project?

选项

  1. A.Enterprise environmental factors
  2. B.Resource management plan
  3. C.Project management plan
  4. D.Procurement statement of work
正确答案:C

解析

解析:关闭合同的相关活动写在采购管理计划里,而采购管理计划是项目管理计划的组成部分。 Rationale:Contract closure activities are described in the procurement management plan, which is a component of the project management plan.