题目
要弄清项目关闭合同需要执行哪些活动,应当查阅哪里?
Where would you look to find what activities should be performed to close out contracts on your project?
选项
- A.Enterprise environmental factors
- B.Resource management plan
- C.Project management plan
- D.Procurement statement of work
解析
解析:关闭合同的相关活动写在采购管理计划里,而采购管理计划是项目管理计划的组成部分。
Rationale:Contract closure activities are described in the procurement management plan, which is a component of the project management plan.
同考点练习题
-
PMP202611-245 · 答案 B
-
PMP202611-362 · 答案 D
-
PMP202611-385 · 答案 C
-
PMP202611-448 · 答案 C
-
PMP202611-512 · 答案 D
-
PMP202611-557 · 答案 A
-
PMP202611-560 · 答案 B
-
PMP202611-627 · 答案 C