题目
项目已完工两个月,某供应商联系项目经理称发票未付。项目经理认为款项已付、采购已关闭。下一步应当做什么?
A project has been completed. Two months later, a vendor contacts the project manager stating that their invoice has not been paid. The PM believes all invoices have been paid and procurements closed out. What should the PM do next?
选项
- A.Tell the vendor that all invoices have been paid since the procurements have been closed
- B.Check the records in the procurement documentation
- C.Reach out to the accounts payable department to see if anyone remembers paying the invoice
- D.Proceed with claims administration to resolve the dispute
解析
解析:采购文档包含签约、执行与关闭协议的全部文件,其中就有发票与付款记录。在下结论前,先查记录。
Rationale:Procurement documentation includes the documents used in signing, executing and closing agreements, including invoices and payment records. Check records before asserting anything.