供方选择与采购流程 · PMP 练习题解析

采购管理 困难 Process 过程域 题号 PMP202611-245

题目

团队需要在两家供应商中做选择:一家报价更低但缺乏业绩,另一家价格更高但在类似工作上业绩良好。最好的做法是什么?
Your team must choose between two suppliers. One is cheaper but unproven; the other is costlier with a strong track record on similar work. What is the BEST approach?

选项

  1. A.Choose the cheaper supplier to minimize cost.
  2. B.Evaluate total value and risk, not price alone, against weighted selection criteria.
  3. C.Choose the costlier supplier because it is safer.
  4. D.Let the sponsor pick without any evaluation criteria.
正确答案:B

解析

解析:以加权标准评估总体价值与风险,才能做出可靠的供方选择决策。只看价格挑最便宜会忽视交付风险;默认选贵的一家则是未经分析就假定安全。 Rationale:Evaluating total value and risk against weighted criteria leads to a sound source-selection decision. Picking the cheapest on price alone ignores delivery risk; defaulting to the costlier one assumes safety without analysis.