供方选择与采购流程 · PMP 练习题解析

采购管理 中等 Process 过程域 题号 PMP202611-557

题目

某已通过资格预审的供应商反复达不到质量标准且沟通消极。项目经理希望今后不再考虑该供应商。最佳做法是:
A project manager has ongoing issues with a pre-qualified seller who repeatedly fails to meet quality standards and is unresponsive. The PM wants to ensure this seller is not considered for future contracts. What is the best course of action?

选项

  1. A.Recommend removing the seller from the prequalified sellers list
  2. B.Capture the information in the issue log
  3. C.Update the project management plan
  4. D.Conduct a procurement audit
正确答案:A

解析

解析:合格供应商名单属于组织过程资产,可作为控制采购的输出予以更新,绩效不佳者可被取消资格并移除。 Rationale:Prequalified seller lists are organizational process assets that can be updated as an output of Control Procurements; poor performers can be disqualified and removed.

同考点练习题