供方选择与采购流程 · PMP 练习题解析

采购管理 中等 Process 过程域 题号 PMP202611-448

题目

管理采购时,采购流程的第一步是:
When managing procurements, the FIRST step in the procurement process is to:

选项

  1. A.Select a seller
  2. B.Sign the contract
  3. C.Plan procurement management: decide what to buy and how
  4. D.Conduct bidder conferences
正确答案:C

解析

解析:先做采购规划——确定自制还是外购,以及采购方式,之后才是选卖方、开会、签约。 Rationale:Plan Procurement Management comes first — determining make-or-buy and the procurement approach.