项目经理正在编制采购管理计划:项目需要一项高度专业的技术服务,市场上仅有两家供应商。最需要关注的采购问题是什么?
A project manager is creating a procurement management plan. The project requires a highly specialised technical service available from only two vendors. Which procurement concern is most significant?

选项

  1. A.Procurement timeline: ensure the RFP is issued early enough.
  2. B.Contract type selection: choose the right contract structure to manage cost.
  3. C.Vendor dependency risk: with only two vendors, loss of either creates a critical single-source risk. Mitigation strategies (dual contracts, contractual exit provisions, knowledge transfer requirements) must be built into the procurement plan.
  4. D.Price negotiation: limited competition allows vendors to inflate prices.
正确答案:C

解析

解析:C 正确。只有两家可选时,最重大的问题是供应商依赖风险:一旦某家无法交付、退出市场或停业会怎样?这是战略层面的采购风险,必须在计划中预设缓解措施。合同类型(B)、时间(A)、价格(D)都是正当的采购考量,但都不如“项目中途失去关键稀缺能力”那么具有存亡意义。 Rationale:C is correct. With only two available vendors, the most significant concern is vendor dependency risk: what happens if one vendor fails to deliver, becomes unavailable or ceases operations? This is a strategic procurement risk that requires specific mitigation built into the plan. While contract type (B), timeline (A) and price (D) are all valid procurement considerations, none is as existentially significant as the risk of losing access to a critical, scarce capability mid-project.