供方选择与采购流程 · PMP 练习题解析

采购管理 困难 Process 过程域 题号 PMP202611-512

题目

项目中途某关键供应商在工料合同下宣布涨价 30%。最佳应对是:
A key vendor announces a 30% price increase mid-project under a T&M contract. BEST response:

选项

  1. A.Accept it silently
  2. B.Terminate immediately without review
  3. C.Pay from contingency without approval
  4. D.Review contract terms, negotiate, assess impact via change control, and consider alternatives
正确答案:D

解析

解析:依合同行事、谈判、走变更控制评估影响,并在承诺前评估替代方案。 Rationale:Follow the contract, negotiate, run impacts through change control, and evaluate alternatives before committing.

同考点练习题