题目
项目中途某关键供应商在工料合同下宣布涨价 30%。最佳应对是:
A key vendor announces a 30% price increase mid-project under a T&M contract. BEST response:
选项
- A.Accept it silently
- B.Terminate immediately without review
- C.Pay from contingency without approval
- D.Review contract terms, negotiate, assess impact via change control, and consider alternatives
解析
解析:依合同行事、谈判、走变更控制评估影响,并在承诺前评估替代方案。
Rationale:Follow the contract, negotiate, run impacts through change control, and evaluate alternatives before committing.