供方选择与采购流程 · PMP 练习题解析

采购管理 中等 Process 过程域 题号 PMP202611-362

题目

项目经理被要求评估:方案是内部自研还是采购商用产品。这属于哪类项目决策?
A project manager is asked to evaluate whether to build a solution internally or purchase a commercial product. This is an example of which type of project decision?

选项

  1. A.A risk management decision: outsourcing transfers risk.
  2. B.A cost management decision: compare internal vs external cost.
  3. C.A resource management decision.
  4. D.A make-or-buy analysis, a procurement planning technique used to determine whether to produce something internally or procure it externally.
正确答案:D

解析

解析:D 正确。自制或外购分析是 PMBOK 中明确的采购规划技术,用于判断产品/服务是内部生产(自制)还是外部采购(外购),考量成本、产能、专业能力、知识产权、时间与战略契合度等因素。成本(B)与风险(A)只是分析中的考量因素,而这类决策在项目管理实践中有专门名称。 Rationale:D is correct. Make-or-buy analysis is a specific procurement planning technique in PMBOK. It evaluates whether to produce a product/service internally (make) or purchase it externally (buy), considering factors such as cost, capacity, expertise, IP, time and strategic fit. While cost (B) and risk (A) are factors within make-or-buy analysis, the decision type itself is specifically named "make-or-buy analysis" in project management practice.