团队建设与团队章程 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-639

题目

为获得最佳人才,项目经理跨国招聘开发人员,如今需要把他们凝聚成一支团队,但预算不够让所有人回总部集中。最佳工具或技术是:
To access the best talent, a PM recruits developers internationally rather than locally. She now needs to build them into a cohesive team, but the budget cannot cover travel to bring everyone to the home office. What is the best tool or technique?

选项

  1. A.Sensitivity analysis
  2. B.Recognition and rewards
  3. C.Virtual teams
  4. D.Colocation
正确答案:C

解析

解析:虚拟团队借助技术搭建在线团队环境来建立凝聚力,在没有差旅预算时是最切实的选择。 Rationale:Virtual teams use technology to create an online team environment that builds cohesion — the practical option when travel budget is unavailable.