团队在两个风险应对方案间权衡:方案一须满足两项标准,成本 5000 美元;方案二须满足四项标准,成本仅 2000 美元。在选择最佳应对时,团队最不可能做哪件事?
A team weighs two risk responses: the first has two criteria that must be met and costs $5,000; the second has four criteria but costs only $2,000. Which action is the team LEAST likely to take in selecting the best response?
选项
- A.Running a Monte Carlo simulation
- B.Performing an alternatives analysis
- C.Conducting a cost-benefit analysis
- D.Using multicriteria decision analysis
解析
解析:备选方案分析、成本效益分析、多标准决策分析都是规划风险应对的常用技术;蒙特卡洛模拟用于量化成本/进度风险,与“选择应对方案”无关。
Rationale:Alternatives analysis, cost-benefit analysis and multicriteria decision analysis are standard in Plan Risk Responses; Monte Carlo simulation models cost/schedule risk quantitatively, not response selection.