风险应对策略选择 · PMP 练习题解析

风险管理 中等 Process 过程域 题号 PMP202611-172

题目

供应商表示若在 10 天内下单设备可享 15% 折扣。你希望确保项目拿到这一好处。这属于哪种风险应对策略?
A supplier offers a 15% discount if you order equipment within the next 10 days. You want to make sure the project gets this benefit. Which risk response is this?

选项

  1. A.Exploit.
  2. B.Accept.
  3. C.Transfer.
  4. D.Mitigate.
正确答案:A

解析

解析:开拓是针对积极风险(机会)的应对策略,目的是确保机会真正实现。减轻和转移用于威胁;接受则不采取特别行动。 Rationale:Exploit is the response for a positive risk (opportunity) that ensures the opportunity is realised. Mitigate and transfer address threats; accept takes no special action.