题目
某风险发生概率低,但一旦发生将是灾难性的,且规避或转移都不可行。最合适的应对策略是什么?
A risk has a low probability but would be catastrophic if it occurred, and avoiding or transferring it is not feasible. What response is most appropriate?
选项
- A.Ignore it because its probability is low.
- B.Accept it passively with no plan at all.
- C.Develop a contingency plan and reserve so you can respond if it occurs.
- D.Treat it as an issue and act on it now.
解析
解析:主动接受并制定应急计划、预留储备,才能为无法规避或转移的低概率高影响风险做准备。无视风险等于暴露于灾难;无计划被动接受过于轻率;当作已发生则提前消耗资源。
Rationale:Active acceptance with a contingency plan and reserve prepares you for a low-probability, high-impact risk you cannot avoid or transfer. Ignoring it leaves you exposed to catastrophe; passive acceptance without a plan is reckless; acting now spends resources on something that has not occurred.