风险应对策略选择 · PMP 练习题解析

风险管理 中等 Process 过程域 题号 PMP202611-119

题目

在一个软件部署项目的执行阶段,项目经理识别到一项高影响风险:由于刚刚公布的市政计划检修,主数据中心可能在迁移周末停电。发生概率中等,但影响是灾难性的(迁移期间数据全损)。最合适的风险应对方式是?
During the execution phase of a software deployment project, the project manager identifies a high-impact risk: the primary data center could lose power during the migration weekend due to scheduled utility maintenance that was just announced. Probability is moderate; impact would be catastrophic (complete data loss during migration). What is the most appropriate risk response?

选项

  1. A.Accept the risk and proceed with the planned migration date
  2. B.Avoid the risk by rescheduling the migration to a weekend without planned utility maintenance
  3. C.Mitigate the risk by renting a backup generator to reduce the probability of power loss during migration
  4. D.Transfer the risk by purchasing insurance to cover potential data loss costs
正确答案:B

解析

解析:当影响是灾难性且存在可行的规避方案(改期)时,规避最为合适,因为它能彻底消除风险。减轻只能降低概率;接受不适用于灾难性风险;保险补偿财务损失但无法阻止数据丢失本身。 Rationale:When impact is catastrophic and a viable avoidance option exists (rescheduling), avoidance is most appropriate because it eliminates the risk entirely. Mitigation only reduces probability, acceptance is inappropriate for catastrophic risk, and insurance covers financial loss but not the data loss itself.