结束项目与阶段收尾 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-633

题目

某装配线建设项目接近完成。项目经理已关闭采购、发布最终报告、更新经验教训库并收集相关方反馈。下一步应当做什么?
An assembly line construction project is nearly complete. The PM closes procurements, shares the final report, updates the lessons learned repository, and obtains stakeholder feedback. What should the PM do next?

选项

  1. A.Provide final payment to the suppliers
  2. B.Send a summary of how the final product achieved the business needs
  3. C.Transfer the completed assembly line to operations
  4. D.Send formal written notice to the vendors that the contracts have been completed
正确答案:C

解析

解析:收尾包含把成果移交给下一阶段或运营;其余选项的动作题干中已完成。 Rationale:Closure includes transferring the product, service or result to the next phase or to operations; the other listed actions were already done.