某风险影响大但发生概率低。项目经理购买保险以覆盖潜在损失。这属于哪种风险应对策略?
A risk has high impact but low probability. The PM buys insurance to cover potential losses. What risk response strategy is used?
选项
- A.Avoid
- B.Mitigate
- C.Transfer
- D.Accept
解析
解析:风险转移是把风险的财务后果转由第三方(如保险公司)承担。
Rationale:Risk transfer shifts the financial consequences of a risk to a third party such as an insurance provider.