风险应对策略选择 · PMP 练习题解析

风险管理 中等 Process 过程域 题号 PMP202611-393

题目

针对一项高概率高影响风险,项目经理要在两种应对策略中选择:A 花费 5 万美元、把概率降到 10%;B 花费 2 万美元、把影响降低 40%。该风险当前 EMV 为 20 万美元(40% 概率 × 50 万影响)。哪项策略价值更高?
A project manager must choose between two risk response strategies for a high-probability, high-impact risk. Strategy A costs $50,000 and reduces probability to 10%. Strategy B costs $20,000 and reduces impact by 40%. The risk currently has EMV of $200,000 (40% probability × $500,000 impact). Which strategy provides better value?

选项

  1. A.Strategy A: reducing probability to 10% is more effective.
  2. B.Strategy A provides better residual risk reduction. After A: EMV = 10% × $500,000 = $50,000, net benefit = $200,000 − $50,000 − $50,000 = $100,000. After B: EMV = 40% × $300,000 = $120,000, net benefit = $200,000 − $120,000 − $20,000 = $60,000. Strategy A delivers greater value despite higher cost.
  3. C.Strategy B: it costs less so it is more cost-efficient.
  4. D.Both strategies provide equal value: choose based on ease of implementation.
正确答案:B

解析

解析:B 正确。策略 A:新 EMV = 10% × 50 万 = 5 万,风险降低额 15 万,净价值 15 万 − 5 万成本 = 10 万。策略 B:新 EMV = 40% × 30 万 = 12 万,风险降低额 8 万,净价值 8 万 − 2 万成本 = 6 万。A 净价值 10 万高于 B 的 6 万,尽管成本更高仍更优。只看成本(C)忽略了风险降低的价值;两者显然不等(D)。 Rationale:B is correct. Strategy A: new EMV = 10% × $500,000 = $50,000, so risk reduction is $150,000; net value = $150,000 − $50,000 cost = $100,000. Strategy B: new EMV = 40% × $300,000 = $120,000, so risk reduction is $80,000; net value = $80,000 − $20,000 cost = $60,000. Strategy A delivers $100,000 net value versus B's $60,000, making A the better choice despite its higher cost. Cost alone (C) ignores risk reduction value. They are clearly not equal (D).