题目
项目经理识别出一项积极风险(机会),若加以利用可降低项目成本 10 万美元。针对积极风险应采取什么应对策略?
A project manager has identified a positive risk (opportunity) that could reduce project cost by $100,000 if exploited. What is the appropriate risk response for a positive risk?
选项
- A.Mitigate: reduce the probability of the opportunity occurring to manage uncertainty.
- B.Exploit: take action to ensure the opportunity definitely occurs and the benefit is realised.
- C.Accept: acknowledge the opportunity and take no action.
- D.Transfer: assign the opportunity to a third party who can benefit from it.
解析
解析:B 正确。对积极风险(机会),最主动的策略是“开拓”,即采取措施确保机会发生。积极风险的其他策略还有:增强(提高概率或影响)、分享(与第三方合作共同获取)、接受(发生则受益)。减轻(A)与转移(D)属于消极风险的应对策略。当机会明确且收益显著时,开拓是最有力的应对。
Rationale:B is correct. For positive risks (opportunities), the most proactive response is Exploit: taking steps to ensure the opportunity happens. Other positive risk responses are: Enhance (increase probability/impact), Share (partner with another party to capture it), and Accept (take the benefit if it happens). Mitigate (A) and Transfer (D) are negative risk responses. Exploit is the strongest positive response when the opportunity is clearly identified and the benefit is significant.