风险应对策略选择 · PMP 练习题解析

风险管理 中等 Process 过程域 题号 PMP202611-059

题目

权变措施与应急计划的区别是什么?
What distinguishes a workaround from a contingency plan?

选项

  1. A.A workaround is planned; contingency is unplanned
  2. B.A workaround addresses unidentified risks; contingency addresses identified risks
  3. C.There is no difference
  4. D.Workarounds apply only in Agile
正确答案:B

解析

解析:应急计划针对已识别的已知风险,权变措施则是对突发问题的应对。 Rationale:Contingency plans address known risks, while workarounds are responses to unexpected issues.