定性风险分析 · PMP 练习题解析

风险管理 中等 Process 过程域 题号 PMP202611-635

题目

你正在确定各单个风险的相对优先级。下列哪项最不可能影响该排序?
You are establishing the relative priorities of individual risks. Which task is LEAST likely to impact this prioritization?

选项

  1. A.Reviewing the assumption log
  2. B.Examining the risk register
  3. C.Researching the stakeholder register
  4. D.Creating the risk report
正确答案:D

解析

解析:风险排序属于实施定性风险分析;假设日志、风险登记册、相关方登记册都是输入,而风险报告是输出,不是输入。 Rationale:Prioritizing risks happens in Perform Qualitative Risk Analysis; the assumption log, risk register and stakeholder register are inputs. The risk report is an output, not an input.