题目
项目经理识别出一项风险:发生概率 40%,一旦发生影响为 8 万美元。实施缓解策略的成本为 2.5 万美元。是否应实施该缓解措施?
A project manager identifies a risk with a 40% probability of occurring and an impact of $80,000 if it does. The cost to implement a mitigation strategy is $25,000. Should the mitigation be implemented?
选项
- A.Yes, because the risk impact of $80,000 is significant and should always be mitigated.
- B.No, because risks should be accepted unless their probability exceeds 50%.
- C.Yes, because the Expected Monetary Value ($32,000) exceeds the mitigation cost ($25,000), making it cost-effective.
- D.No, because the probability is only 40% and the risk may not materialise.
解析
解析:C 正确。EMV = 概率 × 影响 = 0.40 × 80,000 = 32,000。EMV 高于缓解成本 25,000,因此缓解措施具备成本效益,这是定量风险分析的标准做法。只看影响(A)忽略概率;无视低概率风险(D)忽略其期望价值;“50% 阈值”规则(B)并非 PMI 标准。
Rationale:C is correct. EMV = Probability × Impact = 0.40 × $80,000 = $32,000. Since the EMV ($32,000) exceeds the cost of mitigation ($25,000), the mitigation is cost-effective. This is the standard quantitative risk analysis approach. Impact alone (A) ignores probability. Dismissing low-probability risks (D) ignores their expected value. The 50% threshold rule (B) is not a PMI standard.