风险识别与登记册 · PMP 练习题解析

风险管理 中等 Process 过程域 题号 PMP202611-630

题目

团队每月开展风险审计;已识别的风险大量发生,但应对得当、储备充足。一位高管批评项目经理,称风险审计只能由独立外部机构来做。项目经理应如何回应?
A team performs monthly risk audits; many identified risks have been realized, but responses have been appropriate and reserves sufficient. An executive criticizes the PM, saying only independent external resources should perform risk audits. How should the PM respond?

选项

  1. A.Explain that risk audits can be performed either internally or externally as long as they follow the project management plan
  2. B.Agree with the executive and submit a change request to have the audits conducted externally
  3. C.Follow the guidance provided by the executive and hire a team of external auditors
  4. D.Explain that if the current risk audits are not sufficient, then a comprehensive project audit should be carried out
正确答案:A

解析

解析:风险审计评估风险管理过程的有效性,通常由项目团队按风险管理计划规定的频次开展,并不要求必须外部机构执行。 Rationale:Risk audits examine the effectiveness of the risk management process and are typically performed by the project team, at a frequency set in the risk management plan; external auditors are not mandated.

同考点练习题