风险识别与登记册 · PMP 练习题解析

风险管理 困难 Process 过程域 题号 PMP202611-581

题目

某酒店施工项目中,负责某项风险应对策略的人离职,项目经理确定了新的相关方接手。更新相关方登记册之后,下一步应当做什么?
During a hotel construction project, the person responsible for a risk response strategy has left the organization, and the PM identified a new stakeholder to assume those responsibilities. After updating the stakeholder register, what should the PM do next?

选项

  1. A.Update the risk management plan
  2. B.Revise the risk register
  3. C.Notify the PMO of the new stakeholder
  4. D.Execute the Perform Qualitative Risk Analysis process
正确答案:B

解析

解析:每个已识别风险的责任人记录在风险登记册中,责任人变更就必须相应修订登记册。 Rationale:The risk owner for each identified risk is recorded in the risk register; a change of risk owner requires revising it.

同考点练习题