题目
某酒店施工项目中,负责某项风险应对策略的人离职,项目经理确定了新的相关方接手。更新相关方登记册之后,下一步应当做什么?
During a hotel construction project, the person responsible for a risk response strategy has left the organization, and the PM identified a new stakeholder to assume those responsibilities. After updating the stakeholder register, what should the PM do next?
选项
- A.Update the risk management plan
- B.Revise the risk register
- C.Notify the PMO of the new stakeholder
- D.Execute the Perform Qualitative Risk Analysis process
解析
解析:每个已识别风险的责任人记录在风险登记册中,责任人变更就必须相应修订登记册。
Rationale:The risk owner for each identified risk is recorded in the risk register; a change of risk owner requires revising it.