你实施的一项风险应对措施又引发了一个新的、不同的风险。这叫什么,应该怎么处理?
A risk response you implemented has created a new, different risk. What is this called and what should you do?
选项
- A.It is a residual risk; no further action is needed.
- B.It is a secondary risk; identify and plan a response for it.
- C.It is a trigger; simply monitor it.
- D.It is a fallback; activate it immediately.
解析
解析:次生风险由实施应对措施直接引发,必须单独识别并规划应对。残余风险是应对后仍保留的部分;触发条件是预警信号;后备方案是主应对失效时的替代计划。
Rationale:A secondary risk arises directly from implementing a response and must itself be identified and planned for. Residual risk is what remains after a response; a trigger is a warning sign; a fallback is a backup plan if the primary response fails.