题目
现场工程师报告了一起未遂事件:一名工人差点从脚手架跌落。你首先应该做什么?
A site engineer reports a near-miss where a worker almost fell from scaffolding. What should you do first?
选项
- A.Record it and continue work.
- B.Stop the unsafe work, make the area safe, investigate the cause and follow the health and safety policy.
- C.Blame the worker.
- D.Wait to see if it happens again.
解析
解析:健康安全优先于进度。停工、调查并消除原因才能避免真正的事故;忽视未遂事件是严重的合规失职。
Rationale:Health and safety come before schedule. Stopping unsafe work, investigating and fixing the cause prevents an actual accident; ignoring a near-miss is a serious compliance failure.