题目
规划阶段,项目经理要编制一份详细的单个项目风险清单,并识别潜在的风险应对与可能的风险责任人。应当做什么?
In planning a project, a project manager wants to prepare a detailed list of individual project risks and identify potential risk responses along with likely risk owners. What should the project manager do?
选项
- A.Create the risk register
- B.Develop the risk assignments report
- C.Conduct the Perform Quantitative Risk Analysis process
- D.Conduct the Perform Qualitative Risk Analysis process
解析
解析:风险登记册是识别风险的输出,记录已识别的单个风险、潜在责任人与潜在应对措施。
Rationale:The risk register (an output of Identify Risks) records identified individual risks, potential owners and potential responses.