题目
某建筑施工项目执行中,财务总监退休换人,新任总监质疑商业论证的合理性。你已评估新相关方的权力、利益与参与度,并相应更新了相关方登记册与项目管理计划。下一步应当做什么?
With a building construction project underway, the director of finance has retired and been replaced. The new director questions the validity of the business case. You assessed the new stakeholder's power, interest and engagement level and updated the stakeholder register and project management plan accordingly. What should you do next?
选项
- A.Terminate the project because of the flawed business case
- B.Review and update the business case as necessary
- C.Submit a change request to update the stakeholder engagement plan
- D.Modify the assumption log
解析
解析:关于新相关方的权力、利益与参与度判断大多建立在假设之上,这些假设应写入假设日志——它也是识别相关方的输出之一。
Rationale:Much of the power, interest and engagement information about a new stakeholder is based on assumptions, which belong in the assumption log — also an output of Identify Stakeholders.
同考点练习题
-
PMP202611-073 · 答案 B
-
PMP202611-198 · 答案 B
-
PMP202611-241 · 答案 B
-
PMP202611-243 · 答案 A
-
PMP202611-404 · 答案 A
-
PMP202611-564 · 答案 A
-
PMP202611-581 · 答案 B
-
PMP202611-586 · 答案 D