题目
你所在跨职能团队在一家惯用预测型方法的组织中试点自适应方式,需要裁剪进度管理计划模板。最可能需要重点裁剪哪些组成部分?
You are part of a cross-functional team piloting an adaptive approach in an organization that traditionally used predictive. You must tailor the schedule management plan template. Which components are you likely to tailor the most?
选项
- A.The rules of performance measurement, the summary milestones, and the key deliverables
- B.The organizational procedures links, the units of measure, and the project organization charts
- C.The schedule model development, the release and iteration length, and the reporting formats
- D.The project schedule model maintenance, the level of accuracy, and the level of precision
解析
解析:转向自适应方式时,进度模型怎么建、发布与迭代多长、报告什么格式,这三项变化最大。
Rationale:Schedule model development, release/iteration length and reporting formats are the plan components that must change most when moving to an adaptive approach.