题目
项目经理正在识别风险。有成员提出一项风险,项目经理认为概率极低、影响极小。是否应登记到风险登记册?
A project manager is performing Identify Risks. A team member suggests a risk that the project manager believes is highly unlikely and minimal impact. Should it be added to the risk register?
选项
- A.Yes: all identified risks should be documented in the risk register regardless of initial probability assessment. Analysis determines priority; the register is the inventory. Excluding risks during identification creates blind spots.
- B.No: only record risks above a certain probability threshold.
- C.No: low probability/impact risks waste register space and distract from important risks.
- D.Yes, but only if the team member can quantify it precisely.
解析
解析:A 正确。风险识别要尽可能把潜在风险都捞上来,优先级由(定性/定量)分析决定。在识别阶段按项目经理主观判断过滤会产生排除偏差——他判断“极不可能”未必对,提出者可能掌握他不知道的信息。识别阶段并不要求量化(D)。低优先级风险同样应被记录,可归类后被动监控(B、C 均错)。
Rationale:A is correct. Risk identification is about capturing all potential risks: analysis (qualitative and quantitative) is the process that determines priority. Filtering during identification based on the PM's subjective assessment creates exclusion bias. The PM's "highly unlikely" judgment may be wrong; the team member raising it may have knowledge the PM doesn't. Quantification is not required at identification (D). Low-priority risks still deserve documentation. They can be categorised and monitored passively (B, C are both wrong).