风险管理 困难 Process 过程域 题号 PMP202611-631

题目

你在编制风险管理计划,需要确定可接受的整体项目风险暴露水平。首先应当做什么?
You are developing the risk management plan and need to determine the acceptable level of overall project risk exposure. What should you do first?

选项

  1. A.Determine the risk appetites of key project stakeholders
  2. B.Consult the risk exposure register within the organizational process assets
  3. C.Facilitate a brainstorming meeting to develop a comprehensive list of project risks
  4. D.Develop a set of responses to individual project risks to mitigate overall project risk
正确答案:A

解析

解析:相关方的风险偏好(以围绕各目标的可量化阈值表达)决定了可接受的整体风险暴露水平,应写入风险管理计划。 Rationale:Stakeholder risk appetite, expressed as measurable thresholds around each objective, determines the acceptable overall risk exposure and belongs in the risk management plan.