风险管理 中等 Process 过程域 题号 PMP202611-073

题目

你的项目正在处理敏感客户信息,此时出台了新的数据隐私法规。应首先更新哪份文件?
A new data privacy regulation is introduced while your project handles sensitive customer information. Which document should be updated first?

选项

  1. A.Stakeholder register
  2. B.Risk register
  3. C.Project charter
  4. D.Resource management plan
正确答案:B

解析

解析:新合规要求会引入风险,必须先在风险登记册中记录并评估。 Rationale:New compliance requirements introduce risks that must first be documented and assessed in the risk register.