风险识别与登记册 · PMP 练习题解析

风险管理 困难 Process 过程域 题号 PMP202611-243

题目

项目进行到一半,关于某项关键技术的假设被证伪,动摇了原计划。最好的第一步是什么?
Halfway through, your project's assumptions about a key technology prove false, undermining the plan. What is the BEST first action?

选项

  1. A.Reassess the affected plans and risks and adjust the approach.
  2. B.Continue with the original plan to maintain stability.
  3. C.Escalate to the sponsor before analysing anything.
  4. D.Quietly absorb the impact and hope it works out.
正确答案:A

解析

解析:重估受影响计划与风险,才能基于有依据的选项应对被证伪的关键假设。继续原计划等于无视已知无效的假设;未经分析就上报,只会给发起人一个没有选项的难题。 Rationale:Reassessing affected plans and risks lets you adapt to a falsified key assumption with informed options. Continuing the original plan ignores a known invalid assumption; escalating before analysis gives the sponsor a problem with no options.