题目
项目裁剪是大多数项目的重要考量。以下哪项最不可能是裁剪时的考量因素?
Project tailoring is an important consideration for most projects. Which of the following is the least likely consideration?
选项
- A.The project manager's skills and competency
- B.Each project is unique
- C.Addressing competing constraints
- D.The varying level of project governance
解析
解析:裁剪之所以必要,是因为每个项目独特、需要平衡相互竞争的约束,且治理水平各不相同。项目经理个人的技能组合并不是用来裁剪方法论的的项目特征。
Rationale:Tailoring exists because each project is unique, must balance competing constraints, and operates under different governance. The individual manager's personal skill set is not a project characteristic used to tailor the methodology.