题目
项目经理正在规划一款不确定性很高的新软件产品,需求预计会随用户反馈频繁变化。最合适的交付方式是?
A project manager is planning a new software product with high uncertainty. Requirements are expected to change frequently based on user feedback. Which delivery approach is most appropriate?
选项
- A.No formal methodology: use ad-hoc delivery to maximise flexibility.
- B.Agile, use iterative sprints to deliver working software incrementally and incorporate user feedback continuously.
- C.Predictive (waterfall): create a complete requirements document upfront to manage change.
- D.Waterfall with a change control board to manage the expected changes.
解析
解析:B 正确。高度不确定与需求频繁变化正是敏捷适用性的判定条件。迭代交付可持续吸收反馈,避免后期变更的高成本。预测型做法(C、D)把需求定义前置,后期变更代价大,与高不确定性项目的需要相反。临时应变(A)缺乏可预测结果所需的结构。
Rationale:B is correct. High uncertainty and frequent requirement changes are the defining conditions for agile suitability. Iterative delivery allows continuous feedback integration without the cost of late-stage changes. Predictive approaches (C, D) front-load requirements definition and are costly to change later, the opposite of what high-uncertainty projects need. Ad-hoc delivery (A) lacks the structure needed for predictable outcomes.